It is the Clients responsibility to notify a construction project but in practice it may be other duty holders such as the Principal contractor.
If the client is a:
A construction project is notifiable if the construction work is expected to: last longer than 30 working days and have more than 20 workers working at the same time at any point on the project or exceed 500 person days.
We are here to help you so if you have any questions please get in touch below.